Primavera p3 process missing from startup
Primavera p3 process missing from startup








This tutorial will focus on Project type activity codes and this is because Project activity codes are included in an exported xer file. Project activity codes categorize activities based on specific features within a project”. EPS activity codes organize activities within a specific branch or node of the enterprise project structure (EPS). Global activity codes organize activities across all projects in an organization.

#PRIMAVERA P3 PROCESS MISSING FROM STARTUP CODE#

In the Gantt chart shown in figure 01, you will notice that the activities are grouped by our WBS structure shown in figure 02, so in this tutorial, we are going to group the same activities shown in the Gantt chart using different categorisations.Īccording to P6 Help, “An activity code can be one of three types: Global, EPS, or Project. This tutorial is aimed at P6 Beginner or Intermediate level users and all screenshots are from P6 R16.2. In this tutorial, we will explore different ways we can use activity codes to present schedule data. Activity codes (all 3 types Global, EPS & Project) give Planners and Schedulers the flexibility to categorise activities in many ways therefore enabling the grouping, filtering & reporting of activities using custom set of data outside of WBS, Resources and Dates. One drawback of grouping activities only by WBS is that it is a rigid structure with little or no room for manoeuvring and this is where Primavera P6 activity codes come in handy. Planning tools such as Primavera P6 have a feature that enables Schedulers and Planners to replicate the Project WBS and this is why activities in a schedule are predominantly grouped by Work Breakdown Structure. On most projects, the structure of Schedule and Cost performance reporting is based on the Project WBS and the reason for this is not farfetched since WBS is a deliverables-driven hierarchical structure.








Primavera p3 process missing from startup